Add the Activity Type Ex Column

Add the Activity Type EX column to the view so that you can see if a milestone is a start or finish milestone.

To add the Activity Type Ex column, complete the following steps:

  1. Select the S1 // Projects tab.
  2. Right-click an activity column name and click Show Column Chooser.
  3. Drag the Activity Type Ex column from the Column Chooser list to the Activities pane and place it between two existing columns. Acumen will remember your selection and display this column the next time you view this project.
  4. Close the Column Chooser. If you have activity milestones, and as long as your scheduling tool differentiates between start and finish milestones, the Activity Type EX column will display Start Milestone or Finish Milestone.